Design of Temporary Tracks at Ras Al Khair, KSA
Design of Temporary Tracks at Ras Al Khair, KSA
Preliminary and detailed design of temporary track works and their restitution for the construction of culverts 7 and 8 under SAR loop (Ma’aden complex) at Ras Al Khair, KSA.
DESCRIPTION
SYSTRA Canada’s mandate includes:
- All design required for the staged construction of temporary sidings (x4);
- Changes to the existing railway;
- All design required for the staged removal of the temporary sidings and restitution of the existing railway;
- Prepare all necessary scheduling and cost estimate for the execution of the works.